96. The authorization holder must submit to the Minister, for approval, the corrective actions to be taken where any of the following situations occurs:
(1)  a cementing operation provided for in the technical program cannot be carried out;
(2)  no cement return has been observed on the surface where such return was expected;
(3)  a return of drilling fluids indicates that the cement height required for cementing has not been reached;
(4)  there is uncertainty as to reaching the cementing goals.
O.C. 1251-2018, s. 96.
In force: 2018-09-20
96. The authorization holder must submit to the Minister, for approval, the corrective actions to be taken where any of the following situations occurs:
(1)  a cementing operation provided for in the technical program cannot be carried out;
(2)  no cement return has been observed on the surface where such return was expected;
(3)  a return of drilling fluids indicates that the cement height required for cementing has not been reached;
(4)  there is uncertainty as to reaching the cementing goals.
O.C. 1251-2018, s. 96.